Sunday 7 April 2013

Day 109

Apr. 05  2013
Today we have received the pre-plaster inspection result, there're still 20 defects, in which 9 of them being legacies of frame inspection, 11 new finds. Not sure how they can be re-inspected before covering plaster, looks like the plaster will be going up very soon…Nonetheless, we’re quite happy with the progress of the build, credit to our SS.

Thursday 4 April 2013

Day 107

Apr. 04  2013
Today we confirmed with our SS for the pre-plaster inspection date, all the defects discovered in frame inspection will be revisited, fingers crossed.


Day 102

Mar. 30 2013

Day 98

Mar. 26  2013
Brick started, realy pleased by the color and free mortar selections.